STONE rebuilt the exisitng balconies with a new retaiing wall at the perimeter of each balcony at the building.
Post installation of new perimeter balcony walls, STONE scoped the installation of a new pre-cast concrete coping stone to wrap the perimeter of the balcony, contrasting the masonry upon installation.
To comply with NYC DOB code, STONE installed a new top mount glass railing with frosted glass to allow for privacy for the residents.
Balcony reinforcement was installed after the completion of the facade balconies. The structural supports ensured that the additional weight added to the balconies would not cause any structural issues in the future.
Post completion of balcony rebuild, STONE scoped the installation of a deck coating to ensure the protection of the balconies from weathering. STONE also scoped the installation of a new divider to allow for additional privacy for the residents.
STONE scoped the installation of a new scupper and downspout system at all balconies to allow for proper drainage and no pooling to appear on the newly finished balcony decks.
STONE also took into account all other areas of the building to ensure safety all around. Due to issues causing the existing chimney to be unsafe, STONE scoped the replacement of the existing chimney.
STONE also scoped the replacement of existing masonry at the building that exhibited cracking or disrepair.