Upon removing the existing concrete and preparation of the work area, STONE scoped the installation of new steel beams spanning the width of the courtyard for the subsequent installation of new metal decking.
At the time of installation of the new beams, a majority of the beams were pocketed into the existing masonry wall.
Upon the completion of new steel installation, subsequently, new metal decking was installed in preparation for re-bar placement.
Upon completion of metal decking, the contractor proceeded with the installation of new re-bar as noted by STONE's instruction prior to pouring of new concrete.
Post completion of steel beams, decking and rebar- new concrete was poured to create a new slab at the location of courtyard
Upon concrete cure, STONE scoped the installation of a new roofing system to be applied to the newly finalized concrete in ensuring watertightness and protection of sub-cellar below.
Upon the completion of pouring of new concrete slab, STONE proceeded to scope the installation of new fireproofing at all newly installed steel beams and supports.
Apart from the installation of new deck at the courtyard, STONE also scoped the replacement of existing building entrance ramp. STONE ensured that all ADA guidelines were followed in the forming and installation of new ramp.